PMP考試每天一練-2019年PMP考試試題9
|
PMP考試試題一: A human resources(HR) information system is completed according to the project’s specifications. After using the new HR system for the first time, the human resources director states that the old system provided more information than the new system.What should the project manager have done to prevent this situation? A.Defined a contingency plan B.Conducted an appropriate stakeholder analysis C.Created the work breakdown structure D.Initiated a change request 按照項目技術規范,人力資源(HR)信息系統已經完成。在第一次使用新HR系統后,人力資源總監表示舊系統比新系統提供更多的信息。若要防止這種情況,項目經理應該做什么? A.制定應急計劃 B.進行適當的干系人分析 C.創建工作分解結構 D.提出一項變更請求 PMP答案解析:人力資源總監表示舊系統比新系統提供更多的信息,說明這位干系人對新系統期望很高,然后并沒有滿足他。為了避免這種情況,PM應該對干系人進行分析,識別、了解干系人的期望 PMP參考答案:B PMP考試試題二 A project manager evaluates the results of a questionnaire provided to the project sponsor, business analyst, and product designer. The purpose of the questionnaire is to define and clarify the business requirements, as well as align business goals and strategies.This action is part of which of the following knowledge areas? A.Project Integration Management B.Project Scope Management C.Develop Project Charter D.Initiate Project 項目經理評估了提交給項目發起人、業務分析師、產品設計師的問卷調查結果。該問卷調查的目的是為了定義和澄清業務需求,以及將業務目標和戰略保持一致。該項行動屬于下列哪一個知識領域? A.項目整體管理 B.項目范圍管理 C.制定項目章程 D.啟動項目 PMP答案解析:收集需求,屬于范圍管理知識領域 PMP參考答案:B |