PMP考試每天一練-2018年PMP考試試題153
|
PMP考試試題一: Which of the following techniques helps to reduce bias in the data and keeps any individual having undue influence on the outcome? A.Delphi technique B.Brainstorming technique C.Interviewing technique D.Risk review technique 下列哪一項技術有助于減少數據偏見,并避免任何個人對成果產生不當影響? A.德爾菲技術 B.頭腦風暴技術 C.訪談技術 D.風險審查技術 PMP答案解析:德爾菲技術,參考PMBOK PMP參考答案:A PMP考試試題二 To define the work package level of the work breakdown structure (WBS), what should the project team do? A.Analyze and identify all of the project deliverables and their associated work B.Organize and structure all of the project deliverables C.Decompose the project activities into their detailed components D.Analyze and identify all project activities, costs and durations 若要定義工作分解結構(WBS)的工作包層次,項目團隊應該做什么? A.分析并識別所有項目可交付成果及其相關工作 B.組織和構建所有項目可交付成果 C將項目活動分解成詳細的組成部分 D.分析并識別所有項目活動的成本和持續時間 PMP答案解析:制定了統計關系,可用參數估算 PMP參考答案:B |