PMP考試每天一練-2018年P(guān)MP考試試題127
|
PMP考試試題一: During project implementation, the project management notices a high amount of rework. The project manager should consult which of the following for strategies to decrease the amount of rework A.Process improvement plan B.Quality metrics C.Scope statement D.Quality management plan 在項(xiàng)目實(shí)施期間,項(xiàng)目經(jīng)理注意到返工量很大。項(xiàng)目經(jīng)理應(yīng)查閱下列哪一項(xiàng)? A.過(guò)程改進(jìn)計(jì)劃 B.質(zhì)量測(cè)量指標(biāo) C.范圍說(shuō)明書 D.質(zhì)量管理計(jì)劃 PMP答案解析:PMBOK原話:應(yīng)該在項(xiàng)目早期就對(duì)質(zhì)量管理計(jì)劃進(jìn)行評(píng)審,以確保決策是基于準(zhǔn)確信息的。這樣做的好處是,更加關(guān)注項(xiàng)目的價(jià)值定位,降低因返工而造成的成本超支金額和進(jìn)度延誤次數(shù)。 PMP參考答案:D PMP考試試題二 The project management office asks the project manager to formally close the project. The project manager ensures the final product is formally delivered, accepted, and the project documents are updated.The project manager should do which of the following? A.Release all of the resources B.Audit quality control C.Perform quality assurance D.Edit the risk response register 項(xiàng)目管理辦公室要求項(xiàng)目經(jīng)理正式收尾項(xiàng)目。項(xiàng)目經(jīng)理確保最終產(chǎn)品正式交付、驗(yàn)收及項(xiàng)目文件均已更新。項(xiàng)目經(jīng)理應(yīng)該采取下列哪一項(xiàng)措施? A.解散所有資源 B.審計(jì)質(zhì)量控制 C.實(shí)施質(zhì)量保證 D.編輯風(fēng)險(xiǎn)應(yīng)對(duì)登記冊(cè) PMP答案解析:最終產(chǎn)品已經(jīng)移交、文件均已歸檔,根據(jù)收尾流程接下來(lái)應(yīng)該釋放資源 PMP參考答案:A |