PMP考試試題一: A project manager finalizes a project scope statement and realizes it is similar to one completed last year. Based on last year's project, what should the project manager reuse? A.Project charter B.Risk management plan C.Project budget D.Work breakdown structure (WBS) 項(xiàng)目經(jīng)理最終確定項(xiàng)目范圍說明書,并意識(shí)到該項(xiàng)目與去年完成的一個(gè)項(xiàng)目類似。根據(jù)去年的項(xiàng)目,項(xiàng)目經(jīng)理應(yīng)該重復(fù)利用下列哪一項(xiàng)? A.項(xiàng)目章程 B.項(xiàng)目管理計(jì)劃 C.項(xiàng)目預(yù)算 D.工作分解結(jié)構(gòu)(WBS) PMP答案解析:項(xiàng)目管理計(jì)劃則范圍太大,最切合題意的是參考答案D PMP參考答案:D PMP考試試題二 A project manager determines which risks have the greatest impact on the project and plans to use a sensitivity analysis model. The project manager is in which of the following processes? A.Identify risks B.Perform quantitative risk analysis C.Control risks D.Perform qualitative risk analysis 項(xiàng)目經(jīng)理確定了哪些風(fēng)險(xiǎn)對(duì)項(xiàng)目產(chǎn)生的影響最大,并計(jì)劃使用敏感性分析模型。項(xiàng)目經(jīng)理目前處于下列哪一個(gè)過程? A.識(shí)別風(fēng)險(xiǎn) B.實(shí)施定量風(fēng)險(xiǎn) C.風(fēng)險(xiǎn)控制 D.實(shí)施定性風(fēng)險(xiǎn)分析 PMP答案解析:敏感性分析是定量風(fēng)險(xiǎn)分析的工具 PMP參考答案:B |