PMP考試每天一練-2018年PMP考試試題116
|
PMP考試試題一: A project manager is working on a project’s quality management plan. The project manager should consider which of the following when determining the project’s cost of quality(COQ)? A.Training, inspections, rewards, and lost business B.Rewards, inspections, rework, and lost business C.Training, rewards, rework, and lost business D.Training, inspections, rework, and lost business 項目經理正在制定項目的質量管理計劃。在確定項目的質量成本(COQ)時,項目經理應考慮下列哪一項? A.培訓、檢查、獎勵和業務流失 B.獎勵、檢查、返工和業務流失 C.培訓、獎勵、返工和業務流失 D.培訓、檢查、返工和業務流失 PMP答案解析:考慮一致性成本與非一致性成本 PMP參考答案:D PMP考試試題二 During project execution, two teams prove inefficient with systems integration, which causes scheduling issues. What should the project manager do? A.Use collaborative tools. B.Update the issue log. C.Define clear rules. D.Meet with the team supervisor. 項目執行過程中,團隊在系統集成工作中效率低下,已經造成進度問題,項目經理需要如何處理? A.應用協同工具。 B.更新問題日志。 C.制定明確的規則。 D.與團隊主管開會。 PMP答案解析:C參考答案可以理解為建設項目團隊中的“基本規則”這個工具,制定基本規則有利于減少誤解,提高生產力 PMP參考答案:C |