PMP考試每天一練-2018年PMP考試試題75
|
PMP考試試題一: A new project manager works on a project that involves the purchasing of machinery. A colleague worked with the same supplier on a similar project that had a major issue that delayed the machinery delivery. The project manager meets with the colleague to ask about related issue with the supplier.What activity is the project manager performing? A.Plan Procurements B.Plan Risk Management C.Shortlist Supplier D.Plan Schedule 新項目經理管理一個涉及機械采購的項目。一名同事曾經在類似項目上同一個供應商合作過,而該類似項目發生了一個重大問題,延遲了機械交付。項目經理與該同事會面詢問該供應商有關問題。項目經理執行的是哪項活動? A.規劃采購 B.規劃風險管理 C.列出供應商清單 D.規劃進度 PMP答案解析:規劃采購管理包括如何識別預審合格的賣方 PMP參考答案:A PMP考試試題二 A developer assigned to a task with a 10-day duration completes 50% of the task. During a weekly status review session, the project manager discovers a team member wants to work overtime for three day to complete the task.What is the task’s earned value? A.7 days B.6.25 days C.5 days D.4 days 分配到一個為期10天任務的開發人員完成了50%的任務。在每周狀態評審會上,項目經理發現團隊成員希望加班工作三天來完成。該任務該任務的掙值是多少? A.7天 B.6.25天 C.5天 D.4天 PMP答案解析:50%*10=5天 PMP參考答案:C |