1. Your project has a budget of $1.5 million for the first year, $3 million for the second year, $2.2 million of the third year, and $800,000 for the fourth year, Most of the project budget will be spent during

  A. Project plan development

  B. Project plan execution

  C. Integrated change control

  D. Project initiation

  1. 某個項(xiàng)目第一年的預(yù)算是150萬美元。第二年的預(yù)算是300萬美元,第三年的預(yù)算是220萬美元,第四年的預(yù)算是80萬美元。在哪個階段項(xiàng)目的預(yù)算成本最高?

  A. 項(xiàng)目計(jì)劃編制階段

  B. 項(xiàng)目計(jì)劃實(shí)施階段

  C. 全面變更控制階段

  D. 項(xiàng)目啟動階段

  2. You are working on a product development under contract to an automotive company that is building the “next-millennium Yugo.” Initially, the product was defined as “a state-of-the-art personal transportation vehicle.” Later it was described as “a state-of-the-art personal transportation vehicle that requires no gasoline.” Finally, after an all-night hot tub party with the design engineers, it was described as “state-of-the-art personal transportation vehicle that requires no gasoline, costs less than USD15,000, and does not make any noise. This shows the progressive elaboration of product characteristics. But, although the product characteristics are elaborated progressively, they must be coordinated carefully with the

  A. Proper project scope definition

  B. Project stakeholders

  C. Scope change control system

  D. Customer's strategic plan

  2. 你正在為一家汽車公司管理一個開發(fā)新產(chǎn)品的項(xiàng)目。起初,這個產(chǎn)品被定義為”藝術(shù)型的個人交通工具“.后來它又被描述為”不需要汽油的藝術(shù)型個人交通工具“.最后,經(jīng)過與設(shè)計(jì)工程師的詳細(xì)討論后,又將其描述為”不需要汽油、花費(fèi)低于15,000美元而且沒有任何噪聲的藝術(shù)型的個人交通工具“.這表明了產(chǎn)品特征的逐步細(xì)化。但是,盡管產(chǎn)品的特征得到了不斷的細(xì)化,它們還是必須按照下列哪項(xiàng)內(nèi)容來進(jìn)行仔細(xì)調(diào)整?

  A. 適當(dāng)?shù)捻?xiàng)目范圍定義

  B. 項(xiàng)目干系人

  C. 范圍變更控制系統(tǒng)

  D. 客戶戰(zhàn)略計(jì)劃

  3. Your company, a leading pharmaceutical firm, has more project opportunities to pursue than resources available to complete them. You are leading a team to establish a project selection and prioritization method. The team is considering many different management concerns, including financial return, market share, and public perception. You told the team that the most important of the various criteria for building a project selection model is

  A. Capability

  B. Realism

  C. Ease of use

  D. Cost

  3. 你所在的公司是一家在業(yè)內(nèi)處于領(lǐng)先地位的制藥公司。你們有很多項(xiàng)目有待開發(fā),但是目前還沒有足夠的實(shí)力來完成所有的這些項(xiàng)目。而你正率領(lǐng)著一個團(tuán)隊(duì)從事開發(fā)項(xiàng)目篩選方法的工作,你們最終要建立一個項(xiàng)目篩選的模型。你們已經(jīng)將經(jīng)濟(jì)回報(bào)、市場份額和公司的公眾形象等多個方面的因素納入篩選標(biāo)準(zhǔn)的考慮范圍。請你指出在所有的篩選標(biāo)準(zhǔn)中,最重要的一條標(biāo)準(zhǔn)應(yīng)該是:

  A. 公司所具有的完成該項(xiàng)目的實(shí)際能力

  B. 該項(xiàng)目是否具有可行性,是否符合現(xiàn)實(shí)情況

  C. 易用性

  D. 項(xiàng)目成本的大小

  4. Your company, which operates one of the region's largest chemical processing plants, has been convicted of illegally duping toxic substances into the town's river causing alligators to double in size. As a result, the local dog population has been decimated. The court has mandated that the required cleanup activities be completed by February 15. Such a constraint is and example of

  A. A key event

  B. A major milestone

  C. An imposed date

  D. An external dependency

  4. 你所在的公司是當(dāng)?shù)匾患易畲蟮幕S。工廠被指控向河流中傾倒了有毒物質(zhì),導(dǎo)致鱷魚的體積成倍增長。同時(shí)使得當(dāng)?shù)毓返臄?shù)量大量減少。法庭已經(jīng)判決公司在2月15日前必須進(jìn)行清理工作。這樣的外部限制是屬于:

  A. 關(guān)鍵事件

  B. 主要的里程碑式的事件

  C. 強(qiáng)加的日期

  D. 對外部的依賴

  5. You are managing construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. It also requires the use of kryptonite bolts to assemble the piping system. Because kryptonite has a mass density that is 16times its weight, the pipe must be resting in the ground a total of 10 day before the bolts can be installed. In this example, the 10-day period is defined as

  A. Lag

  B. Lead

  C. Float

  D. Slack

  5. 你負(fù)責(zé)管理一個城市用水系統(tǒng)項(xiàng)目。為了避免水管生銹,合同上要求使用金的管道設(shè)備,此外還要用不銹鋼鉚釘來組裝這些管道。根據(jù)某些技術(shù)要求,這些管道旋轉(zhuǎn)好以后要過10天才能鉚釘。這10天被稱作:

  A. 滯后時(shí)間

  B. 前置時(shí)間

  C. 浮動時(shí)間

  D. 松弛時(shí)間

網(wǎng)站sitemap

日韩精品一区二区三区三区免费_欧美理论片在线_久久精品人人做人人爽97 _欧美日韩亚洲视频

PMP團(tuán)購導(dǎo)航
遠(yuǎn)程PMP團(tuán)購
北京PMP團(tuán)購
上海PMP團(tuán)購
廣州PMP團(tuán)購
深圳PMP團(tuán)購
江浙PMP團(tuán)購
西部PMP團(tuán)購
其他城市團(tuán)購



PMP題庫
主站蜘蛛池模板: 日韩欧美在线播放视频| 久久天天躁狠狠躁夜夜躁2014| 国产素人在线观看| 国产福利精品在线| 日韩五码在线观看| www.久久草| 国产免费成人av| 国产在线观看不卡| 久久国产精品免费观看| 欧美精品在线极品| 日本一区二区在线播放| 日韩精品 欧美| 不卡伊人av在线播放| 国产精品久久久久久久午夜| 久久精品视频网站| 久久6免费高清热精品| 国产一区二区在线播放 | 亚洲国产欧洲综合997久久| 精品人妻人人做人人爽| 久久精品亚洲国产| 久久国产乱子伦免费精品| 欧美亚洲免费高清在线观看| 日本精品va在线观看| 欧美精品久久久| 欧美精品在线免费| 久久99精品久久久久久久久久| 亚洲精品欧洲精品| 日韩中文字幕亚洲精品欧美| 日韩欧美不卡在线| 热久久99这里有精品| 久久久精品视频在线观看| 国产精品久久久久久久7电影 | 日韩精品极品视频在线观看免费| 99国产在线| 国产精品91在线观看| 中文字幕日韩一区二区三区不卡| 精品国模在线视频| 国产精品国产亚洲伊人久久| 国产日韩中文字幕在线| 国产精品久久久久久久av电影| 99久久国产免费免费|