PMP考試練習(xí)題(30)

轉(zhuǎn)載者:PMP團(tuán)購(gòu)網(wǎng)      發(fā)布時(shí)間:2012/7/17        點(diǎn)擊: 3820

1 Which of the following impacts the critical path?

  A Changing the task duration.

  B Reduce the free float of an activity.

  C Executing a backward pass

  D A or B

  E None of the above.

  ans:A

  2 The range of time allowed for an activity to be completed in is the _____.

  A Planned time (Duration)。

  B Float time (LS - ES, or LF - EF)。

  C Critical time (when ES = LS, or EF = LF)。

  D Scheduled time (LF - ES)。

  E Event.

  ans:D

  3 Free float is the amount of time that an activity may be delayed with out affecting the _____.

  A Early start of the succeeding activities.

  B Late start of the succeeding activities.

  C Project finish.

  D Cost of the project.

  E None of the above.

  ans:A

  4 Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.

  A 0.5

  B 1

  C 1.8

  D 2.2

  E 2.8

  ans:C

  5 In crashing a task, you would focus on:

  A As many tasks as possible.

  B Non critical tasks.

  C Accelerating performance of tasks on critical path.

  D Accelerate performance by minimizing cost.

  E A and D.

  ans:C

  6 Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

  A 8

  B 8.8

  C 9.1

  D 9.7

  E 10.5

  ans:B

  7 Using the WBS in the Special window, an instance of a work package is:

  A Build house

  B Excavate

  C Prepare Foundation

  D B and C

  E None of the above

  ans:E

  8 All of the following are categories of a milestone in a schedule except:

  A End date.

  B Contract dates.

  C Key events scheduled.

  D Imposed dates.

  E Task duration.

  ans:E

  9 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.

  A Increases.

  B Is not affected by

  C Does not require

  D Is heavily dependent upon

  E Is the only means of determining

  ans:D

  10 Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.

  A Reduce.

  B Eliminate.

  C Double

  D Increase

  E Not affect

  ans:D

  11 The key purpose of project control is to:

  A Plan ahead for uncertainties.

  B Generate status reports.

  C Keep the project on track.

  D Develop the project road map.

  E All of the above.

  ans:C

  12 Fast tracking means to:

  A Speed up a project through parallel tasks.

  B Swap one task for another.

  C Reduce the number of tasks if possible.

  D B and C.

  E None of the above.

  ans:A

  13 As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:

  A Insignificant.

  B Reduced.

  C Unchanged.

  D Increased.

  E Doubled.

  ans:C

  14 The purpose of a dummy activity in an activity-on-arrow diagram is to:

  A Identify a task that could be replaced by another.

  B Take the slack time into account.

  C Show a task that is not necessarily needed.

  D Denote a milestone.

  E Show a dependency relationship.

  ans:E

  15 On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:

  A $-100

  B $100

  C $-150

  D $150

  E 85%

  ans:C

  16 A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:

  A 1.50%

  B 33.00%

  C 75%

  D 67%

  E None of the above.

  ans:B

  17 Resource leveling will often affect the project by making it:

  A Shorter.

  B Longer

  C More responsive to customer needs.

  D A and C

  E B and C.

  ans:B

  18 Using the figure in the Special window, The slacktime in Activity “G” is _____ weeks.

  A 2

  B 3

  C 4

  D 5

  E 7

  ans:C

  19 Using the figure in the Special window, Activity “D” has a latest start time of _____ weeks and a latest finish time of _____ weeks.

  A 2, 10

  B 4, 12

  C 6, 14

  D 7, 15

  E 9, 17

  ans:A

  20 Using the figure in the Special window, Activity “L” has an early start time of _____ weeks and an early finish time of _____ weeks.

  A 11, 13

  B 12, 14

  C 13, 15

  D 14, 16

  E 15, 17

  ans:E

網(wǎng)站sitemap

日韩精品一区二区三区三区免费_欧美理论片在线_久久精品人人做人人爽97 _欧美日韩亚洲视频

PMP團(tuán)購(gòu)導(dǎo)航
遠(yuǎn)程PMP團(tuán)購(gòu)
北京PMP團(tuán)購(gòu)
上海PMP團(tuán)購(gòu)
廣州PMP團(tuán)購(gòu)
深圳PMP團(tuán)購(gòu)
江浙PMP團(tuán)購(gòu)
西部PMP團(tuán)購(gòu)
其他城市團(tuán)購(gòu)



PMP題庫(kù)
主站蜘蛛池模板: 91国产在线免费观看| 亚洲欧洲国产日韩精品 | 亚洲五月六月| 精品国内产的精品视频在线观看| 久久精品视频中文字幕| 中文字幕精品在线播放| 视频一区不卡| 婷婷久久五月天| 欧美日韩一区二区三| 亚洲免费久久| 高清av免费一区中文字幕| 日韩av免费看网站| 99久久99久久精品国产片| 91久久大香伊蕉在人线| 日韩精品极品视频在线观看免费| 日本丰满少妇黄大片在线观看| 91精品国产综合久久香蕉922| 97久久国产亚洲精品超碰热| 日本免费高清一区| 欧美精品一区在线发布| 国产欧美日韩亚洲| 99国产在线| 91精品中文在线| 色天天综合狠狠色| 性欧美精品一区二区三区在线播放V| 日韩av中文字幕第一页| 日韩中文字幕一区二区| 国产精品入口免费视频一| 99在线免费视频观看| 国产精品综合久久久| 亚洲综合在线中文字幕| 久久久久久久免费| 在线视频不卡国产V| 日韩精品成人一区二区在线观看| 99色精品视频| 国产日韩一区二区在线观看| 精品国产一区二区三区在线| 国产精品久久久久久久久久久不卡| 亚洲尤物视频网| 国产中文字幕视频在线观看| 亚洲在线视频福利|