以下城市均已開通:
關閉
當前位置:PMP團購網 > PMP考試資料 > 正文

PMP考試練習題(29)

轉載者:PMP團購網      發布時間:2012/7/17        點擊: 3673

1 The critical path in a network is the path that:

  A Has the greatest degree of risk.

  B Will elongate the project if the activities on this path take longer than anticipated.

  C Must be completed before all other paths.

  D All of the above.

  E A and B only.

  ans:B

  2 The major difference between PERT and CPM networks is:

  A PERT requires three time estimates whereas CPM requires one time estimate.

  B PERT is used for construction projects whereas CPM is used for R & D.

  C PERT addresses only time whereas CPM also includes cost and resource availability.

  D PERT requires computer solutions whereas CPM is a manual technique.

  E PERT is measured in days whereas CPM uses weeks or months.

  ans:A

  3 A calendar that identifies when a project may be performed on an activity is called a:

  A Project calendar.

  B Resource calendar.

  C Milestone point.

  D Key point.

  E Work unit.

  ans:A

  4 Planning activities such that predetermined resource availability pools are not exceeded is called:

  A Resource leveling.

  B Manpower leveling.

  C Resource limited planning.

  D Manpower planning.

  E Manpower contingency planning.

  ans:C

  5 A comparison of completion status to baseline is referred to as _____.

  A Earned value measurement.

  B Percent complete.

  C ACWP.

  D BCWS

  E None of above.

  ans:A

  6 The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:

  A Slack

  B Free float.

  C Restricted float.

  D Level float.

  E Lag

  ans:E

  7 Overlapping activities on a project, such as design and construction, is referred to as:

  A Fast tracking

  B Risk conversion.

  C Parallel management.

  D Process improvement.

  E Synchronous manufacturing

  ans:A

  8 A computer tape which contains historical project information is called ____ tape.

  A Database

  B Baseline.

  C Archive.

  D Lessons learned.

  E Life cycle summary.

  ans:C

  9 Which method shown below is acceptable for reducing cost or shortening the schedule?

  A “Crashing”

  B Changing scope.

  C Performing activities in parallel rather than in series.

  D All of the above.

  E A and C only.

  ans:D

  10 In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.

  A Increase, decrease.

  B Increase, increase

  C Increase, increase or decrease.

  D Decrease, decrease.

  E Decrease, increase.

  ans:B

  11 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.

  A Allocation.

  B Partitioning

  C Leveling

  D Quantification.

  E None of above.

  ans:A

  12 Smoothing out resource requirements from period to period is called resource _____.

  A Allocation.

  B Partitioning

  C Leveling.

  D Quantification

  E None of above.

  ans:C

  13 Guidelines for estimating time durations include:

  A Assuming a normal level of labor and equipment.

  B Assuming a normal work week.

  C Using consistent time units

  D Using past actual durations as guides.

  E All or part of each of the above.

  ans:E

  14 Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?

  A PERT

  B ADM

  C PDM

  D All of the above.

  E A and C only.

  ans:C

  15 In the PDM, common constraints include:

  A Start-to-start

  B Finish-to-start

  C Finish-to-finish

  D B and C only

  E A, B, and C.

  ans:E

  16 Activities with zero time duration are referred to as:

  A Critical path activites.

  B Noncritical path activities.

  C Slack time activities.

  D Dummies

  E None of above.

  ans:D

  17 In the arrow diagramming method (ADM), _____ do not consume time or resources.

  A Events.

  B Activities

  C Slack elements.

  D B and C only.

  E All of the above.

  ans:A

  18 On a precedence diagram, the arrow between two boxes is called:

  A An activity.

  B A constraint.

  C An event.

  D The critical path.

  E None of above.

  ans:B

  19 A project element which lies between two events is called:

  A An activity.

  B A critical path method.

  C A slack milestone.

  D A timing slot.

  E A calendar completion point.

  ans:A

  20 The basic terminology for networks includes:

  A Activities, events, manpower, skill levels and slack.

  B Activities, documentation, events, manpower and skill levels.

  C Slack, activities, events, and time estimates.

  D Time estimates, slack, sponsorship involvement, and activities.

  E Time estimates, slack time, report writing, life cycle phases, and crashing times.

  ans:C

日韩精品一区二区三区三区免费_欧美理论片在线_久久精品人人做人人爽97 _欧美日韩亚洲视频

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 久久免费少妇高潮久久精品99| 亚洲狠狠婷婷综合久久久| 亚洲一区中文字幕在线观看| 狠狠干 狠狠操| 青青精品视频播放| 日韩欧美一区二区三区四区五区 | 国产欧美日韩精品在线观看| 欧美一级免费看| 日日噜噜噜噜夜夜爽亚洲精品| 亚洲精品第一区二区三区| 一区二区三区四区欧美日韩| 国产精品国产自产拍高清av水多| 精品国产第一页| 久久av一区二区| 日韩中文字幕第一页| 日韩一级片免费视频| 久久亚洲欧美日韩精品专区| 日韩在线视频观看| 国产免费成人av| 国产日韩欧美在线观看| 丝袜美腿精品国产二区| 欧美精品久久久| 久久人妻精品白浆国产| 91成人福利在线| 真实国产乱子伦对白视频| 国产日韩欧美在线| 国产精品一久久香蕉国产线看观看| 91精品视频在线| 久久在线免费观看视频| 欧美久久久久久V| 日韩免费黄色av| 国产精品美女在线播放| 国产成人精品视| 欧美日韩在线观看一区| 热久久视久久精品18亚洲精品| 日韩一区国产在线观看| 精品视频导航| 日韩一区在线视频| 欧洲日韩成人av| 国产综合第一页| 狠狠色狠狠色综合人人|