PMP考試每天一練-2019年P(guān)MP考試試題123
|
PMP考試試題一: A company plans to open a factory in a new region to expand its overseas market. Its competitors already operate numerous factories in that region. These companies have been categorized by the government as Low-pollution enterprises."What should the project sponsor do prior to initiating the project? A. Investigate the customer's strategic plan. B. Obtain the local government's support. C. Examine the company's strategic plan. D. Appraise the business case. 某公司計(jì)劃開拓海外市場,在某洲的東南地區(qū)新建一個(gè)工廠。其競爭對手已經(jīng)在該地區(qū)擁有了多個(gè)工廠。政府將該類企業(yè)歸類為輕度污染企業(yè)。在開始發(fā)起前,項(xiàng)目發(fā)起人應(yīng)該先做以下哪項(xiàng)工作? A.調(diào)查客戶戰(zhàn)略計(jì)劃。 B.尋求當(dāng)?shù)卣С帧?/span> C.參考公司戰(zhàn)略計(jì)劃。 D.進(jìn)行商業(yè)論證評估。 PMP答案解析:項(xiàng)目啟動時(shí)要進(jìn)行商業(yè)論證來幫助確定是否立項(xiàng)。 PMP參考答案:D PMP考試試題二 During a board of directors meeting, a possible project delay is discussed. The board of directors asks for recommended steps to accelerate the project.This is an example of what type of change request? A. Defect repair B. Corrective action C. Preventive action D. Fast tracing 董事會上討論了一個(gè)可能的項(xiàng)目延期情況。董事長要求提出建議措施來加快項(xiàng)目進(jìn)度。這屬于哪種變更請求類型的實(shí)例? A.缺陷補(bǔ)救 B.糾正措施 C.預(yù)防措施 D.快速跟進(jìn) PMP答案解析:可能發(fā)生延期,并沒有真的延期,提出建議加快項(xiàng)目進(jìn)度確保不延期。 PMP參考答案:C |