PMP考試每天一練-2019年PMP考試練習題99
|
PMP考試練習題一: A quality audit identifies nonconformities for several deliverables on the critical path. Upon completion of corrective actions, the project manager needs to report the results to the change control board (CCB).What should the project manager do to validate conformity? A. Complete quality checklists. B. Inspect the changes. C. Update the change 1Oq. D. Complete a statistical sampling. 質量審計識別到關鍵路徑上多個可交付成果的不一致之處。在完成糾正措施后,項目經理需要將結果報告給變更控制委員會(CCB)。若要核實一致性,項目經理應該怎么做? A.完成質量核對表。 B.檢查變更 C.更新變更日志。 D.完成統計抽樣。 PMP答案解析:通過統計抽樣來進行檢測 PMP參考答案:D PMP考試練習題二 A company’s executive team identifies a product that is underperforming and needs to be replaced. The project sponsor asks the project manager to initiate a new project to develop the replacement product.What should the project manager do first? A. Submit the project charter to the project sponsor for approval. B. Work with the project sponsor to identify the high level requirements for the replacement product. C. Develop the project management plan. D. Indentify the project stakeholders who will be involved in the development of the replacement product. 一家公司的執行團隊識別到一項產品表現不佳,需要替換。項目發起人要求項目經理啟動一項新項目,開發替換產品。項目經理首先應該做什么? A.向項目發起人提交項目章程,用于批準。 B.與項目發起人合作,識別替換產品的髙層次需求。 C.制定項目管理計劃 D.識別涉及替換產品并發工作的項目干系人 PMP答案解析:啟動新項目,首先應該制定項目章程。 PMP參考答案:A |