PMP考試每天一練-2019年P(guān)MP考試試題91
|
PMP考試試題一: A project manager discovers that half of the project team members assigned to task B must first complete task A. What should the project manager use to adjust the schedule? A. Resource histogram B. Resource leveling C. Resource smoothing D. Resource optimization 項(xiàng)目經(jīng)理發(fā)現(xiàn)被分配到任務(wù)B的一半項(xiàng)目團(tuán)隊(duì)成員必須首先完成任務(wù)A。項(xiàng)目經(jīng)理應(yīng)該使用什么來(lái)調(diào)整進(jìn)度計(jì)劃? A.資源直方圖 B.資源平衡 C.資源平滑 D.資源優(yōu)化 PMP答案解析:推薦 D答案,包括了資源平衡(用于關(guān)鍵路徑中的資源調(diào)整)與資源平滑(用于非關(guān)鍵路徑中的資源調(diào)整)。 PMP參考答案:D PMP考試試題二 Before developing a project charter, the project manager works with a consultant and subject matter experts to determine any constraints. Which of the following techniques did the project manager use? A.Lessons learned B.Historical information C.Strategic plan D.Expert judgment 制定項(xiàng)目章程之前,項(xiàng)目經(jīng)理與一名顧問(wèn)和主題專(zhuān)家一起合作確定任何制約因素。項(xiàng)目經(jīng)理使用了下列哪一項(xiàng)技術(shù)? A.經(jīng)驗(yàn)教訓(xùn) B.歷史信息 C.戰(zhàn)略計(jì)劃 D.專(zhuān)家判斷 PMP答案解析:和主題專(zhuān)家一起合作,這是專(zhuān)家判斷 PMP參考答案:D |