PMP考試每天一練-2019年P(guān)MP考試試題75
|
PMP考試試題一: A project manager is assembling team and wants to ensure all the cost estimates are accurate. Which of the following tools should be used to ensure accurate estimates? A. Sensitivity and reserve analysis B. Pareto diagrams and earned value analysis C. Cost aggregation and funding limit reconciliation D. Delphi analysis and expert judgment 項(xiàng)目經(jīng)理正在組建一個(gè)團(tuán)隊(duì),并希望確保所有成本估算都正確。應(yīng)使用下列哪一項(xiàng)工具來確保估算準(zhǔn)確? A.敏感性和儲(chǔ)備分析 B.帕累托圖和掙值分析 C.成本匯總和資金限制平衡 D.德爾菲分析和專家判斷 PMP答案解析:選項(xiàng)D是估算成本的工具。選項(xiàng)C是制定預(yù)算的工具 PMP參考答案:D PMP考試試題二 A customer asks a project manager to add a protection mechanism for a power supply system currently under construction. This request will incur sizeable costs. However, if this mechanism is not added, it may cause substantial liability and financial risks for future operations teams. What should the project manager do? A. Solicit expert judgment from all possible channels. B. Complete a sensitivity analysis to assess potential impact on the project. C. Conduct a probabilistic analysis. D. Perform an expected monetary value (EMV) analysis with the assumption of risk-neutral. 客戶要求項(xiàng)目經(jīng)理為一個(gè)目前正處于施工的供電系統(tǒng)增加保護(hù)機(jī)制。這項(xiàng)請(qǐng)求將產(chǎn)生相當(dāng)大的成本。但是,如果不添加這種機(jī)制,它可能會(huì)導(dǎo)致未來運(yùn)營(yíng)團(tuán)隊(duì)產(chǎn)生大量的責(zé)任和財(cái)務(wù)風(fēng)險(xiǎn)。項(xiàng)目經(jīng)理應(yīng)該怎么做? A.從所有可能的渠道征求專家判斷。 B.完成敏感性分析,以評(píng)估對(duì)項(xiàng)目的潛在影響。 C.進(jìn)行概率分析。 D.在風(fēng)險(xiǎn)中立的假設(shè)前提下,執(zhí)行預(yù)期貨幣價(jià)值(EMV)分析。 PMP答案解析:根據(jù)題干,四個(gè)答案中最好的答案是EMV分析,通過分析給出決策路徑 PMP參考答案:D |