PMP考試每天一練-2019年PMP考試試題67
|
PMP考試試題一: A new project manager joins a project and observes that team members constantly discuss minor scope amendments via email and phone. A review of project documents fails to identify any reference to these amendments.What plan should be strengthened? A. Change management B. Stakeholder management C. Quality management D. Communications management 一位新項目經理加入項目,觀察到團隊成員不斷通過電子郵件和電話討論小的范圍修改。但查閱項目文檔卻未發現有提及任何此類修改。應加強哪份計劃? A.變更管理 B.干系人管理 C質量管理 D溝通管理 PMP答案解析:有范圍修改,卻沒有任何文檔記錄,題干描述明確顯示需要優化變更管理 PMP參考答案:A PMP考試試題二 Due to an organizational change, some functional human resources will no longer be available work on the project. The organization lacks internal resource to fill the vacancies A.Redistribute the workload across the remaining functional resources B.Assess external resource C.Reschedule the project D.Escalate this human resource issue to the project sponsor 由于組織變更,有些職能人力資源不再可能為項目工作。該組織缺乏內部資源來填補空缺。若要解決這個資源問題,項目經理應該怎么做? A.在剩余的職能資源中重新分配工作量 B.評估外部資源 C.重新制定項目進度計劃 D.將這個人力資源問題上報給項目發起人 PMP答案解析:如果執行組織不能提供為完成項目所需的人員,就需要從外部獲得所需的服務 PMP參考答案:B |