PMP考試試題一: A project manager discovers that the critical ratio is 0.7. What does this indicate? A. The cost performance Index (CPI) is better than planned. B. The CPl is worse than planned C. The project's progress is worse than planned. D. The project's progress is better than planned.. 項(xiàng)目經(jīng)理發(fā)現(xiàn)臨界比是0.7。這說明什么? A成本績效指數(shù)(CPI)比計(jì)劃好 B.CPI比計(jì)劃差 C.項(xiàng)目進(jìn)展比計(jì)劃差 D.項(xiàng)目進(jìn)展比計(jì)劃好 PMP答案解析:臨界比的計(jì)算方法是CPI*SPI,臨界比等于0.7,說明項(xiàng)目進(jìn)展不好 PMP參考答案: PMP考試試題二 After confirming the availability of human resource and obtaining teams for project assignments, the project manager discovers that the resources will not sufficiently meet the project schedule. The project manager meets with a functional manager who agrees to make additional resources available for the duration of the project.What tool or technique does the project manager use? A.Negotiation B.Acquisition C.Pre-assignment D.Co-location 確認(rèn)人力資源可用性并獲得執(zhí)行項(xiàng)目任務(wù)的團(tuán)隊(duì)后,項(xiàng)目經(jīng)理發(fā)現(xiàn)資源不足以滿足項(xiàng)目進(jìn)度計(jì)劃,項(xiàng)目經(jīng)理與職能經(jīng)理開會(huì),職能經(jīng)理同意為項(xiàng)目工期增加可用資源。項(xiàng)目經(jīng)理是用的是什么工具或技術(shù) A.談判 B.招募 C.預(yù)分派 D.集中辦公 PMP答案解析:“項(xiàng)目經(jīng)理與職能經(jīng)理開會(huì)”來獲得資源,這是談判 PMP參考答案:A |