PMP考試每天一練-2019年PMP考試試題31
|
PMP考試試題一: A project manager has an idea for a new service which will enable their company to conduct business within a new market segment. After consultations, networking, market analysis, and project assessment, the project manager believes there is a foundation to further define the idea for the new service.What should the project manager do next? A.identify risks B.collect requirements C.define the high-level scope D.create the work breakdown structure 項目經理對一項新服務有個創意,能讓其公司在一個新細分市場中開展業務,經過咨詢、交流、市場分析和項目評估后,項目經理認為存在進一步定義該項新服務創意的基礎。項目經理接下來應該怎么做? A.識別風險。 B.收集需求。 C.定義高層次范圍。 D.創建工作分解結構。 PMP答案解析:開始一個新項目要制定項目章程,C是章程中的內容 PMP參考答案:C PMP考試試題二 A project stakeholder inquires about a high-priority task that needs to be delivered within the quarter. What should the project manager provide to the stakeholder? A.Project management plan B.Project documents C.Work performance information D.Work performance data 項目干系人詢問一個需要在本季度內交付的高優先級任務。項目經理應該向項目干系人提供什么文件? A.項目管理計劃 B.項目文件 C.工作績效信息 D.工作績效數據 PMP答案解析:工作績效信息中會工作數據以及偏差結果的呈現 PMP參考答案:C |