PMP考試每天一練-2019年PMP考試試題6

轉載者:PMP團購網      發布時間:2019/1/25        點擊: 2466

PMP考試試題一:

While creating the project’s status report, the project manager notices that all the variance measures are positive numbers. What is the project’s status?

A.Under budget and ahead of schedule

B.Under budget and behind schedule

C.Over budget and ahead of schedule

D.Over budget and behind schedule

創建項目狀態報告時,項目經理注意到所有偏差衡量均為正數。項目目前的狀態是什么?

A.低于預算并超前于進度

B.低于預算但落后于進度

C.超出預算單超前于進度

D.超出預算并落后于進度

PMP答案解析:CV、SV均大于0,說明成本結余、進度提前

PMP參考答案:A

PMP考試試題二

During a software project, s execution phase, the project team discovers that four integration testing cycle lasts four weeks instead of two. To reduce the impact on schedule, the team lead recommends performing parallel testing cycles.What should the project manager do next?

A. Review the quality management plan

B. Conduct the perform quality assurance process

C. Conduct a quality audit with all project stakeholders

D. Eliminate two of the four testing cycles

在一個軟件項目的執行階段,項目團隊發現每四個集成測試周期持續時間為四周,而非兩周。為減 少對項目進度計劃的影響,團隊負責人建議執行并行測試周期。項目經理下一步應該怎么做?

A.審查質量管理計劃

B.開展實施質量保證過程

C.與所有項目干系人開展質量審計

D.去除四個測試周期的其中兩個

PMP答案解析:快速跟進要控制風險,確保工作質量,預防缺陷、建立信心,所以要實施質量保證

PMP參考答案:B

閱讀本文的人還閱讀了:
PMP考試報名資格怎么審查?
PMP認證培訓怎么選機構?
PMP培訓機構是什么?
PMP考試時間具體是什么?
PMP考試報名時間是什么?
PMP教材是什么?

日韩精品一区二区三区三区免费_欧美理论片在线_久久精品人人做人人爽97 _欧美日韩亚洲视频

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 国内精品久久久久伊人av| 国产精品一 二 三| 日韩欧美亚洲v片| 国产精品91在线| 久久av在线播放| 国产精品自产拍在线观看中文| 久久综合五月天| 精品久久久久久无码中文野结衣| 亚洲一区二区三区免费观看| 国产精品区免费视频| 国产精品久久久久久久久久久久| 日韩精品一区二区三区丰满| 日韩一级在线免费观看| 亚洲欧美日韩不卡| 日韩av高清不卡| 久久久久久国产精品美女| 久久精品99无色码中文字幕| 欧美一级视频一区二区| 久99久视频| 国产精品久久九九| 日韩av大片在线| 国产一区喷水v| 亚洲一区精品电影| 久久久久国产精品www| 国产欧美日韩中文字幕在线| 欧美激情久久久久久| 久久色精品视频| 国产一区二区视频在线观看| 中文字幕精品一区日韩| 美日韩精品免费视频| 国产精品久久久久91| 亚洲91精品在线观看| 国产欧美日韩中文| 日本高清视频一区二区三区| 国产精品美腿一区在线看| 日韩综合视频在线观看| 国产在线高清精品| 日本不卡免费高清视频| 亚洲专区中文字幕| 精品国偷自产在线视频| 日韩一区二区三区高清|