PMP考試每天一練-2018年P(guān)MP考試試題160
|
PMP考試試題一: A project is 40% complete. To increase team productivity and improve the implementation of processes. Which of the following should the project manager conduct? A.Brainstorming session B.Risk audit C.Process optimization audit D.Quality audit 項目已完成40%。若要提高團隊生產(chǎn)力,改善流程的執(zhí)行。項目經(jīng)理應(yīng)該開展下列哪一項? A.頭腦風(fēng)暴法 B.風(fēng)險審計 C.過程優(yōu)化審計 D.質(zhì)量審計 PMP答案解析:質(zhì)量審計的目標:積極、主動地提供協(xié)助,以改進過程的執(zhí)行,從而幫助團隊提高生產(chǎn)力。 PMP參考答案:D PMP考試試題二 Two co-workers disagree on the products and services that will be delivered by a project.To address the disagreement, the project manager should refer to which of the following? A. Project statement of work (SOW) B. Human resource management plan C. Quality management plan D. Project management plan 兩名同事對一個項目交付的產(chǎn)品和服務(wù)意見不一致。若要解決這個分歧,項目經(jīng)理應(yīng)該查閱下列哪一份文件? A.工作說明書(SOW) B.人力資源管理計劃 C.質(zhì)量管理計劃 D.項目管理計劃 PMP答案解析:查詢之前的經(jīng)驗教訓(xùn)提高個人交付項目的成功率 PMP參考答案:A |