PMP考試每天一練-2018年PMP考試試題151
|
PMP考試試題一: During final product testing of a two-year project, an application is scheduled to be implemented within the next month. The project manager discovers that a mandatory deliverable was overlooked in the project management plan; however, the development team states that it will only take 15 days to complete.What should the project manager do? A.Re-validate the scope B.Perform integrated change control C.Adjust the schedule to cover the change D.Perform crashing to meet the deadline 在一個為期兩年項目的最終產品測試期間,一項應用程序安排在下個月實施。項目經理發現項目管理計劃中忽略了一個強制性可交付成果。然而,開發團隊說只需花15天能夠完成。項目經理應該怎么做? A. 重新核實范圍 B. 實施整體變更控制 C. 調整進度計劃包含變更 D. 執行趕工,滿足期限要求 PMP答案解析:“忽略了一個強制性可交付成果”,說明與原計劃有偏差,需要變更 PMP參考答案:B PMP考試試題二 The most likely cost for an activity is US$2,000. The optimistic cost is US$1,500. The pessimistic cost is US$3,100.What would be the expected activity cost? A.US$2,000 B.US$2,100 C.US$2,300 D.US$3,100 某項活動的最可能成本是2000美元。樂觀成本是1500美元。悲觀成本是3100美元。那么預期活動成本是多少? A.2000美元 B.2100美元 C.2300美元 D.3100美元 PMP答案解析:三點估算公式:(1500+4*2000+3100)/6=2100 PMP參考答案:B |