PMP考試每天一練-2018年P(guān)MP考試試題132
|
PMP考試試題一: In a matrix organization, an additional resource is required to complete an unfinished task, the project manager requests the resource from a functional manager.To obtain the functional manager’s approval, which of the following should the project manager include in the resource request? A.Required skills, resource cost, and duration B.Resource name, start date, and duration C.Type of activity, start date, and duration D.Required skills, start date, and duration 在矩陣式組織中,要求一名額外的資源完成未完成的任務(wù)。項(xiàng)目經(jīng)理向職能經(jīng)理申請?jiān)撡Y源。為獲得職能經(jīng)理的批準(zhǔn),項(xiàng)目經(jīng)理應(yīng)將下列那一項(xiàng)包含進(jìn)資源請求中? A.需要的技能、資源成本和持續(xù)時間 B.資源姓名、開始日期和持續(xù)時間 C.活動類型、開始日期和持續(xù)時間 D.需要的技能、開始日期和持續(xù)時間 PMP答案解析:組建項(xiàng)目團(tuán)隊(duì)的工具:多標(biāo)準(zhǔn)決策分析,技能、成本、可用性。參考PMBOK PMP參考答案:A PMP考試試題二 A project has an eight-month schedule. Based on the table, what should be the new duration to complete the project? Project length(months) 8. 00 Budget at completion (BAC) US$20000 Actual cost for work performed (ACWP) US$8000 Actual cost (AC) Budgeted cost for work performed(BCWP) US$7500 Earned value(EV) Budgeted cost for work scheduled (BCWS) US$8500 Planned Value(PV) A.1 month B.8.6 month C.9.1 month D.12month 項(xiàng)目工期為八個月。根據(jù)表格,完成項(xiàng)目的新工期為多少? 項(xiàng)目工期(月) 8.00 完工預(yù)算(BAC) 20000美元 已完工作實(shí)際成本(ACWP) 8000美元 實(shí)際成本(AC) 已完工作預(yù)算成本(BCWP) 7500美元 掙值(EV) 計(jì)劃工作預(yù)算成本(BCWS) 8500美元 計(jì)劃價(jià)值(PV) A. 1個月 B. 8.6個月 C. 9.1個月 D. 12個月 PMP答案解析:新工期=8/SPI=8*8500/7500=9.1 PMP參考答案:C |