PMP考試每天一練-2018年PMP考試試題106
|
PMP考試試題一: During a project's closure phase, the project manager creates a project summary and review in which team members share lessons learned, what tool or technique is the project manager using? A.Summary reports B.Expert judgment C.Analytical techniques D.Meetings 在項目收尾階段,項目經理和他的團隊進行了項目總結和檢討,其中包含團隊成員各自在項目中的收獲和成功分享。他采用了哪種工具? A匯總報告 B.專家判斷 C.分析技術 D.會議 PMP答案解析:結束項目或階段,通過會議進行經驗教訓的總結等 PMP參考答案:D PMP考試試題二 The project management plan is distributed to all key stakeholders. However, the project sponsor and the customer have comments and want to make some changes.Who should receive this feedback and take the appropriate actions A.Change control board B.Project sponsor C.Project manager D.Project team 已將項目管理計劃分發給所有關鍵干系人。然而,項目發起人和客戶有意見,并希望做一些改進。誰應負責收取該反饋并采取適當的行動? A.變更控制委員會 B.項目發起人 C.項目經理 D.項目團隊 PMP答案解析:實施整體變更控制過程貫穿項目始終,項目經理對此負最終責任 PMP參考答案:C |