PMP考試每天一練-2018年P(guān)MP考試試題103
|
PMP考試試題一: Due to technical issues, a project is stopped in the early stages. When closing the project, what should the project manager do? A.Update and archive the work breakdown structure B.Update and archive the project charter C.Document and archive the lessons learned D.Inform the technical supervision about the issues 因?yàn)榧夹g(shù)問(wèn)題,項(xiàng)目在早期階段停止了,項(xiàng)目收尾時(shí),項(xiàng)目經(jīng)理應(yīng)該怎么做? A.更新并存檔工作分解結(jié)構(gòu) B.更新并存檔項(xiàng)目章程 C.記錄并存檔經(jīng)驗(yàn)教訓(xùn) D.將相關(guān)問(wèn)題通知技術(shù)主管 PMP答案解析:項(xiàng)目收尾時(shí)要記錄并總結(jié)經(jīng)驗(yàn)教訓(xùn) PMP參考答案:C PMP考試試題二 During a project meeting, a team member identifies and submits a risk to the project manager. After an evaluation of the risk, the project team determines the impact, probability, and a risk response.Before performing these activities, what process must be completed? A. Plan Risk Management B. Identify Risks C. Perform Quantitative Risk Analysis D. Plan Risk Responses 在項(xiàng)目會(huì)議上,一名團(tuán)隊(duì)成員識(shí)別到一個(gè)風(fēng)險(xiǎn),并將其提交給項(xiàng)目經(jīng)理。在評(píng)估完風(fēng)險(xiǎn)后,項(xiàng)目團(tuán)隊(duì)確定了影響、發(fā)生概率和風(fēng)險(xiǎn)應(yīng)對(duì)措施。執(zhí)行這些活動(dòng)之前,必須完成哪個(gè)過(guò)程? A. 制定風(fēng)險(xiǎn)管理計(jì)劃 B. 識(shí)別風(fēng)險(xiǎn) C. 實(shí)施定量風(fēng)險(xiǎn)分析 D. 制定風(fēng)險(xiǎn)應(yīng)對(duì)計(jì)劃 PMP答案解析:在識(shí)別風(fēng)險(xiǎn)、風(fēng)險(xiǎn)分析、規(guī)劃風(fēng)險(xiǎn)應(yīng)對(duì)之前,要做的是規(guī)劃風(fēng)險(xiǎn)管理 PMP參考答案:A |