PMP考試每天一練-2018年PMP考試試題93
|
PMP考試試題一: The project manager wants to consider developing the project internally or outsourcing the work to a third-party contractor. Which of the following should the project manager do next? A.Cost-benefit analysis B.Make-or-buy analysis C.SWOT analysis D.Vendor bid analysis 項目經理希望考慮內部開發項目還是將工作外包給第三方承包商。項目經理接下來應執行下列哪一項? A.成本效益分析 B.自制或外購分析 C.SWOT分析 D.賣方投標分析 PMP答案解析:考慮內部開發還是將工作外包給第三方承包商,自制或外購分析 PMP參考答案:B PMP考試試題二 During a project’s planning phase, the project manager of project A learns that specific equipment is required for an activity. It is the project manager of project B’s responsibility to acquire and install this equipment.What type of dependency reflects the relationship between the activity and the required equipment? A.Discretionary internal B.Discretionary external C.Mandatory internal D.Mandatory external 在項目規劃階段,項目A的項目經理了解到某項活動需要使用特殊設備。而采購安裝該設備是項目B項目經理的責任。哪一種依賴關系類型反映了這項活動與所需設備之間的關系? A.選擇性內部依賴關系 B.選擇性外部依賴關系 C.強制性內部依賴關系 D.強制性外部依賴關系 PMP答案解析:項目A依賴于這項特殊設備,因此是強制性。而這項設備是另一個項目B采購的,所以是外部關系 PMP參考答案:D |