PMP考試每天一練-2018年PMP考試試題90
|
PMP考試試題一: A project is delayed because one item in the equipment specification is obsolete. A replacement will require a longer lead time.To avoid this situation, the project manager should have done which of the following during project planning? A.Prepared a contingency plan B.Selected a more reliable supplier C.Spent more effort on the Identify Risks process D.Ensured that the item is not on the critical path 由于設備技術規范的某一項被淘汰,項目延期。更換將需要較長的交付實踐。為避免這種情況,項目經理在項目規劃期間應完成下列哪一項? A.制定應急計劃 B.選擇更為可靠的供應商 C.在識別風險過程上花費更多的精力 D.確保該項不在關鍵路徑上 PMP答案解析:在識別風險過程上花費更多的精力,盡早識別風險,避免因更換導致項目延期。A是風險,B是減輕,D就算在非關鍵路徑上一旦發生也可能會延期項目 PMP參考答案:C PMP考試試題二 Due to an increased rate of natural disasters along a flood plain, a warehouse director wants to initiate a project to review and update the disaster management plan. Which of the following should the project manager use to identify the project risks? A. Risk probability and impact assessment B. Brainstorming C. Risk rating and ranking D. Flowchart 由于洪泛平原沿線發生自然災害的頻率增加,倉庫主任希望啟動一個項目,審查和更新災難管理計劃。項目經理應該使用下列哪一項來識別項目風險? A.風險概率與影響評估 B.頭腦風暴 C.風險評級和排序 D.流程圖 PMP答案解析:信息收集技術頭腦風暴,是識別風險的工具 PMP參考答案:B |