PMP考試每天一練-2018年PMP考試試題89
|
PMP考試試題一: Which of the following audits will be performed by the project management office to validate that the project is using the correct project management methodology? A.Compliance B.Performance C.Best practices D.Quality 下列哪一項審計將由項目管理辦公室執行來核實項目是否使用正確的項目管理方法? A.合規性 B.績效 C.最佳實踐 D.質量 PMP答案解析:通過質量審計來確保使用了正確的流程,方法和政策 PMP參考答案:D PMP考試試題二 After approval of a project’s scope and specifications, the customer asks for the addition of a few minor deliverables to increase the final product’s value. What should the manager do next? A. Reject the change unless the customer agrees to increase the project budget B. Assess the impact of the change and issue a change request C. Ask the project team to confirm if these are minor changes and, if so, implement then D. Implement the changes to strengthen the relationship with the customer 批準項目范圍和技術規范之后,客戶要求增加一些次要可交付成果,提升最終產品的價值。項目經理下一步應該怎么做? A.拒絕變更,除非客戶同意增加項目預算 B.評估變更的影響,并簽發變更請求 C.要求項目團隊確認是否屬于次要變更,如果是,則實施這些變更 D.實施變更,加強與客戶的關系 PMP答案解析:客戶要求變更,應該遵循變更管理流程,先提出變更請求、然后評估變更影響 PMP參考答案:B |