PMP考試每天一練-2018年PMP考試試題79
|
PMP考試試題一: The conditions which allow a contract to be mutually ended prior to its completion are identified in which of the following? A.Project management plan B.Negotiated settlements C.Termination clause D.Statement of work 允許合同在完成之前由雙方終止的條件稱為下列哪一項? A.項目管理計劃 B.協商解決 C.終止條款 D.工作說明書 PMP答案解析:合同終止條款規定了雙方對提前終止合同的權利和責任 PMP參考答案:C PMP考試試題二 A project manager works on a project to retain a customer, s business. The quality team measures quality and identifies areas where the project fails to meet the requirements and specifications.Which of the following processes is the project’s quality team applying? A. Perform Quality Assurance B. Control Quality C. Statistical and Variance Analyses D. Plan Quality Management 項目經理正在從事一個保留客戶業務的項目。質量團隊測量質量,確定了項目未能滿足要求和技術規范的一些方面。項目質量團隊應用的是下列哪一個過程? A. 實施質量保證 B. 控制質量 C. 統計和偏差分析 D. 計劃質量管理 PMP答案解析:確定了項目未能滿足要求和技術規范的一些方面,這是針對結果 PMP參考答案:B |




