PMP考試每天一練-2018年P(guān)MP考試試題47
|
PMP考試試題一: The customer of a delayed project requests an additional feature. The feature can be built with no significant impact to the schedule or cost.What should the project manager do next? A.Accept the proposal as compensation to the customer for the project delay B.Deny the request immediately without further consultation C.Put the feature on hold, as a future enhancement D.Create a change request and submit to the change control board for consideration 某個(gè)延期項(xiàng)目的客戶請(qǐng)求增加功能。該功能可以在不對(duì)進(jìn)度或成本產(chǎn)生重大影響的情況下嵌入。項(xiàng)目經(jīng)理下一步該怎么做? A.接受該提議作為對(duì)客戶項(xiàng)目延期的補(bǔ)償 B.在不進(jìn)一步咨詢的情況下,立即拒絕該請(qǐng)求 C.擱置該功能,作為未來改進(jìn)功能 D.創(chuàng)建一份變更請(qǐng)求,并將其提交給變更控制委員會(huì)考慮 PMP答案解析:直接接受、直接拒絕、擱置,都是不對(duì)的,排除ABC。應(yīng)該遵循變更管理流程首先提交變更請(qǐng)求 PMP參考答案:D PMP考試試題二 The management team identifies a new risk that could potentially delay to a deliverable by six weeks. In response to this, what should the project manager do first? A. Quantity the impact B. Analyze the variance C. Update the risk register D. Implement corrective actions 管理團(tuán)隊(duì)識(shí)別可能會(huì)延遲某個(gè)可交付成果六周時(shí)間的新風(fēng)險(xiǎn)。為應(yīng)對(duì)這種情況,項(xiàng)目經(jīng)理應(yīng)該首先做什么? A. 量化影響 B. 分析偏差 C. 更新風(fēng)險(xiǎn)登記冊(cè) D. 執(zhí)行糾正措施 PMP答案解析:識(shí)別到新風(fēng)險(xiǎn),首先應(yīng)該更新到風(fēng)險(xiǎn)登記冊(cè)中 PMP參考答案:C |