PMP考試試題一: Midway through a project's execution phase, a team member proposes changes to provide more flexibility and additional features. Project requirements define only the need for a simple solution that is less flexible. Implementing these changes will result in a delay. What should the project manager do? A. Reject the proposal, and follow the project management plan. B. Escalate it to the project sponsor via a change request. C. Agree to the changes, and arrange for more resources at maintain the schedule. D. Incorporate the changes, and update the project management plan. 在項(xiàng)目執(zhí)行階段中途一名團(tuán)隊(duì)成員提出變更建議,能提供更多的靈活性和額外功能。項(xiàng)目需求定義僅需要具有較少靈活性的簡單解決方案,而實(shí)施這些變更將導(dǎo)致延期。項(xiàng)目經(jīng)理應(yīng)該怎么做? A.拒絕該建議,并遵循項(xiàng)目管理計(jì)劃。 B.通過變更請求將該問題上報(bào)給項(xiàng)目發(fā)起人。 C.同意變更,并安排更多的資源來保持進(jìn)度計(jì)劃。 D.包含變更,并更新項(xiàng)目管理計(jì)劃。 PMP答案解析:項(xiàng)目范圍管理要求做且只做完成項(xiàng)目所需要的全部工作,要按照定義的需求來實(shí)施項(xiàng)目,避免渡金 PMP參考答案:A PMP考試試題二 Transferring the property of purchased software licenses to a company, s primary users is an activity of which of the following? A. Closing procurement B. Closing a project C. Validating scope D. Executing a project 將購買的軟件許可證財(cái)產(chǎn)轉(zhuǎn)移到一家公司的主要用戶屬于下列哪一項(xiàng)活動(dòng)? A.采購收尾 B.項(xiàng)目收尾 C.核實(shí)范圍 D.執(zhí)行項(xiàng)目 PMP答案解析:采購結(jié)束即采購收尾 PMP參考答案:A |