PMP考試每天一練-2018年PMP考試試題28
|
PMP考試試題一: A project manager assesses the economics of a discretionary change in project scope by evaluating its impact on the project's value. Where should the project manager find the discount rate for this calculation? A. Project funding requirements B. Cost management plan C. Project charter D. Lessons learned 項目經理通過評估項目范圍中的一項自由變更對項目價值的影響來評估該變更的經濟意義。項目經理應從哪里找到這項計算的折現率? A.項目資金需求 B.成本管理計劃 C.項目章程 D.經驗教訓 PMP答案解析:成本管理計劃給出作為成本管理的方法論及相關要求,包括折現率等 PMP參考答案:B PMP考試試題二 Internal conflicts among some team members could potentially delay the project, What should the project manager do next? A. Address the conflicts early and privately B. Delay the conflict to assess if it will affect the project at a later stage C. Escalate the conflict to the functional managers D. Consult the human resource management plan and take corrective actions 一些團隊成員的內部沖突可能延遲項目。項目經理下一步該怎么做? A.提前并私下解決沖突 B.延遲沖突,評估其是否將會在后期影響項目 C.將沖突上報給職能經理 D.查看人力資源管理計劃并采取糾正措施 PMP答案解析:沖突的首選解決方法是依靠沖突的當事人自己解決 PMP參考答案:A |