PMP考試每天一練-2018年PMP考試試題25
|
PMP考試試題一: During the early phases of a project, the project manager realizes that the project budget is dependent on the price of raw materials. What should the project manager do next? A.Update the scope statement B.Buy the raw materials before prices increase C.Update the risk register D.Ask for a change request 在項目早期階段,項目經理意識到項目預算取決于原材料的價格。項目經理接下來應該怎么做? A.更新范圍說明書 B.在價格上漲之前采購原材料 C.更新風險登記冊 D.要求變更請求 PMP答案解析:“項目預算取決于原材料的價格”說明具有一定的不確定性,這是風險 PMP參考答案:C PMP考試試題二 The project manager plans to purchase concrete for a building construction project, the quality of the materials is consistent among all vendors, leaving price as the major difference.Which type of vendor response should the project manager request? A.Request for information B.Request for proposal C.Statement of work D.Request for quotation 項目經理計劃為一個建設施工項目采購混凝土。所有供應商的材料質量都一樣,只有價格有主要區別。項目經理應向供應商請求那種應對類型 A.信息請求 B.建議邀請書 C.工作說明書 D.報價邀請書 PMP答案解析:題干說供應商的材料質量都一樣,只有價格有區別,選報價邀請書 PMP參考答案:D |