PMP考試每天一練-2018年PMP考試試題19
|
PMP考試試題一: A two-year software implementation project approaches completion. Which of the following should the project manager use for formal closure? A.Final product, work breakdown structure, and project management plan B.Status reports, risk register, and work breakdown structure C.Project management plan, risk register, and change log D.Project charter, scope statement, and change log 一個為期兩年的軟件實施項目接近完工。項目經理應使用下列哪一項正式收尾? A.最終產品,工作分解結構和項目管理計劃 B.狀態報告,風險登記冊和工作分解結構 C.項目管理計劃,風險登記冊和變更日志 D.項目章程,范圍說明書和變更日志 PMP答案解析:參考項目收尾的輸入。 PMP參考答案:A PMP考試試題二 After learning of a potential project change, the project manager performs an impact analysis. The project manager then presents the change request to the change control board (CCB) to review and approval. The CCB approves the change and releases it for implantation.What should the project manager update first? A.Risk register B.Project charter C.Project management plan D.Quality management plan 獲知一個潛在項目變更后,項目經理執行了影響分析。項目經理然后提交變更請求供變更控制委員會(CCB)審查和批準。CCB批準變更并準予實施。項目經理首先更新那一項內容? A.風險登記冊 B.項目章程 C.項目管理計劃 D.質量管理計劃 PMP答案解析:變更請求獲得了CCB批準后,首先更新項目管理計劃。 PMP參考答案:C |