PMP考試每天一練--PMP考試試題188
|
PMP考試試題一: A project is ahead of schedule, which the budget is overrun. Which of the following could be the schedule and cost performance indices? A. schedule performance index is 1.20 and the cost performance index is 1.15 B. schedule performance index is 1.10 and the cost performance index is 0.09 C. schedule performance index is0.95 and the cost performance index is 0.85 D. schedule performance index is 0.90 and the cost performance index is 1.10 某項目進度超前,但是預算超支,下列哪一項可能是項目進度和成本績效指數? A. 進度績效指數為1.20;成本績效指數為1.15 B. 進度績效指數為1.10;成本績效指數為0.09 C. 進度績效指數為0.95;成本績效指數為0.85 D. 進度績效指數為0.90;成本績效指數為1.10 PMP答案解析:掙值管理(7.4.2.1)P217 PMP參考答案:B. 進度績效指數為1.10;成本績效指數為0.09 PMP考試試題二: Lack of communication and unsolved arguments imply: A. Complicated project. B. Crashed schedule. C. Inefficient project team. D. Undefined responsibility of project team. 缺少溝通和爭議未解決意味著: A. 項目錯綜復雜 B. 進度計劃失靈 C. 項目小組效率不高 D. 項目小組職責不明確 審題:此題涉及溝通和爭議,屬于人力資源管理內容。 定位:人力資源管理的拓展。 PMP參考答案:C. 項目小組效率不高 |