PMP考試每天一練--PMP考試試題184
|
PMP考試試題一: Because you are working under a firm-fixed-price contract,management wants you to submit the final invoice and close out the contract as soon as possible. Before final payment on the contract can be authorized, you must A. Prepare a contract completion statement B. Audit the procurement process C. Update and archive contract records D. Settle subcontracts 你正在依據一個固定價格合同工作,管理層要求你提交一份最終發票,盡快結束合同。在根據合同最終付款得到批準之前,你必須 A. 準備一份合同完成陳述 B. 對采購流程進行審計 C. 更新和整理合同記錄 D. 處理分包合同 PMP答案解析:結束采購引言(12.4)P387 PMP參考答案:D. 處理分包合同 PMP考試試題二: If project A has an NPV of $30,000 and project B of $50,000, what is the opportunity cost if project B is selected? A. $23,000. B. $30,000. C. $20,000. D. $50,000. 如果項目 A 的凈現值為 30000 美元,項目 B 的為 50000 美元,那么選取項目 B 的機會成本是多少? A. $23,000 B. $30,000 C. $20,000 D. $50,000 審題:此題關鍵句“機會成本” “選取項目 B” 定位:成本管理的擴展 解析:機會成本(Opportunity Cost):是指為了得到某種東西而所要放棄另一些東西的最大價值。 凈現值(Net Present Value)是一項投資所產生的未來現金流的折現值與項目投資成本之間的差值。選項目B則放棄項目A PMP參考答案:B. $30,000 |