PMP考試試題一: The seller tells you that your activities have resulted in an increase in their costs. You should: A. recommend a change to the project costs. B. have a meeting with management to find out what to do. C. ask the seller for supporting information. D. deny any wrongdoing. 賣方告訴你,你的經營活動使得賣方的成本增加了。你應該: A. 建議變更項目成本 B. 會見管理層,找到解決辦法 C. 尋求賣方提供支持信息 D. 拒絕承認做錯事 PMP參考答案:C. 尋求賣方提供支持信息 PMP答案解析:采購/成本問題 PMP考試試題二: Senior management asks the project manager how the project would be affected if two resources were removed from the project. To calculate a response, the project manager should complete: A. Resource leveling. B. What-if scenario analysis. C. Schedule compression. D. Fast tracking. 高級管理層詢問項目經理,如果從項目中抽調兩項資源是否會對項目造成影響。項目經理應該完成以下哪項來回答管理層的問題: A.資源平衡。 B.假設情景分析。 C.進度壓縮。 D.快速跟進。 審題: 此題的關鍵是“從項目中抽調兩項資源”。 定位: 規劃過程組·項目時間管理·制定進度計劃·假設情景分析 解析: 此題考的是假設情景分析的概念。 PMP參考答案:B.假設情景分析。 |