PMP考試每天一練--PMP考試試題131
|
PMP考試試題一: The buyer and seller bargain on a fixed price plus incentive fee contract, the aim cost of the contract is 200000 dollars, the aim profit is 30000 dollars, the aim price is 230000 dollars, the two parties also consult the highest price at 270000 dollars, the halve ratio is 70/30, if the seller accomplished the fact cost is 170000 dollars, how much profit should the buyer pay for theseller? A. $21000 B. $35000 C. $39000 D. $51000 買方和賣方商定了一個總價加激勵的合同,合同的目標成本是200000美元,目標利潤是30000美元,目標價格是230000美元,雙方還商定了最高價格為270000美元,分享比率為70/30,如果賣方完成合同的實際成本為170000美元,那么買方要向賣方支付多少利潤? A. 21000美元 B. 35000美元 C. 39000美元 D. 51000美元 PMP參考答案:C. 39000美元 PMP答案解析:規劃采購輸-合同類型 ( 12.1.1.9 ) P362 PMP考試試題二: A project manager is quantifying risks for her project. Several of her experts are off-site, but wish to be included in the risk assessment portion of the project. How can this be done? A. Use Monte Carlo simulation through Internet as a tool. B. Apply the critical path method. C. Do a brainstorming. D. Apply the Delphi technique. 一名項目經理正在為自己的項目進行量化。幾位參與項目的專家都不在現場,但是希望參與項目風險評估工作。如何實現這一點? A. 依托因特網,使用 Monte Carlo模擬方法。 B. 使用關鍵路徑法。 C. 進行頭腦風暴。 D. 使用 Delphi技術。 審題:此題的關鍵是“幾位參與項目的專家都不在現場” ,“項目風險評估”。 定位:規劃過程組·項目風險管理·識別風險·信息收集技術 解析:D選項德爾菲技術是組織專家就某個專題達成一致意見的一種方法。項目風險專家匿名參與,符合題干所說的幾位參與項目的專家都不在現場的條件。A、B選項不屬于可用于風險識別信息收集技術中的工具。C選項需要專家在場才可以做。 PMP參考答案:D. 使用 Delphi技術。 |