PMP考試試題一: The project manager is developing a project plan, on short notice project sponsor asks the project manager to create an initial rough estimate of project cost to satisfy requirements for the upcoming fiscal budget. The project manager uses which of the following for estimating the project cost? A. Bottom-up estimating B. Three-point estimating C. Analogous estimating D. Parametric modeling 項目經理正在制定一個項目計劃。項目贊助人得知后,立即讓項目經理針對項目成本開展初始粗略評估,以滿足未來財政預算的需求。項目經理采用下列哪一項評估項目成本? A. 自下而上估算 B. 三點結算 C. 類比估算 D. 建立參數模型 PMP參考答案:C. 類比估算 PMP答案解析:估算活動歷時工具:類比估算(6.5.2.2)P169 PMP考試試題二: After analyzing the status of your project, your determine that the earned value (EV) is lower than the planned value (PV). What should you expect as an outcome if this trend continues? A. The actual cost will be lower than planned. B. The estimate at completion will be lower than planned. C. The project will finish behind schedule. D. The project will finish below the original cost estimate. 分析完項目狀況后,你發現項目的掙值(EV)低于計劃值(PV)。如果這個趨勢一直發展下去,結果將會如何? A.實際成本低于計劃成本。 B.完工估算低于計劃值。 C.項目完工日期將會落后預計進度。 D.項目完工的最終成本要比原先估算的要低。 審題: 此題的關鍵字為“掙值EV低于計劃值PV”。 定位: 監控過程組.成本管理·7.4.2 控制成本: 工具和技術 解析: EV低于PV說明SV是處于負數狀態,SV處于小于零時,是進度落后的表現,會出現項目進度(完工日期)落后預計進度的過程。C項滿足此說法,其他選項都是描述的成本問題。 PMP參考答案:C.項目完工日期將會落后預計進度。 |