PMP考試每天一練--PMP考試試題-90
|
PMP考試試題一: In a fixed price (FP) contract, the fee or profit is: A. unknown. B. part of the negotiation involved in paying every invoice. C. applied as a line item to every invoice. D. determined with the other party at the end of the project. 在固定價(jià)格(FP)合同中,費(fèi)用或利潤(rùn)是: A. 不知道的 B. 涉及支付每張發(fā)票的談判的一部分 C. 作為排列項(xiàng)應(yīng)用到每張發(fā)票 D. 和另外一方在項(xiàng)目期末一起確定的 PMP參考答案:A. 不知道的 PMP答案解析:合同類(lèi)型(12.1.1.9)P362 PMP考試試題二: During project executing, the project manager is spending a lot of time solving problems that arise. It would be BETTER for the project manager to transfer his efforts to: A. Having the team solve the problems, thus freeing his time to hold more meetings. B. Executing the project management plan and making sure the quality management plan is viable. C. Identifying additional risks and following the risk management process. D. Performing sensitivity analysis on past problems and transferring them to other projects. 項(xiàng)目實(shí)施過(guò)程中,項(xiàng)目經(jīng)理把主要時(shí)間放在解決問(wèn)題上。其實(shí),項(xiàng)目經(jīng)理應(yīng)該把精力轉(zhuǎn)移到: A.讓團(tuán)隊(duì)成員處理發(fā)生的問(wèn)題,這樣自己就會(huì)有很多時(shí)間來(lái)召開(kāi)會(huì)議。 B.實(shí)施項(xiàng)目管理計(jì)劃,并確保質(zhì)量管理計(jì)劃的可行性。 C.識(shí)別額外的風(fēng)險(xiǎn),遵循風(fēng)險(xiǎn)管理程序。 D.實(shí)施敏感性分析,并將問(wèn)題轉(zhuǎn)移到其它項(xiàng)目上。 審題: 題干關(guān)鍵字“項(xiàng)目經(jīng)理把主要時(shí)間放在解決問(wèn)題上”,只有發(fā)現(xiàn)問(wèn)題,找出問(wèn)題根本原因,才能解決問(wèn)題。 定位: 規(guī)劃過(guò)程組.風(fēng)險(xiǎn)管理·11.6 控制風(fēng)險(xiǎn) 解析: 項(xiàng)目經(jīng)理不需要把精力放在開(kāi)會(huì)上,頻繁的開(kāi)會(huì)只會(huì)浪費(fèi)項(xiàng)目的時(shí)間(選項(xiàng)A)。項(xiàng)目經(jīng)理的角色是指導(dǎo)和控制,并不是直接的實(shí)施管理計(jì)劃(選項(xiàng)B)。敏感性分析(選項(xiàng)D)在實(shí)施定量風(fēng)險(xiǎn)分析時(shí)已經(jīng)完成了,現(xiàn)在是控制風(fēng)險(xiǎn)階段。只有選項(xiàng)C應(yīng)該解決問(wèn)題的根本原因,在監(jiān)控風(fēng)險(xiǎn)的時(shí)候要識(shí)別額外的風(fēng)險(xiǎn),遵循風(fēng)險(xiǎn)管理程序。 PMP參考答案:C.識(shí)別額外的風(fēng)險(xiǎn),遵循風(fēng)險(xiǎn)管理程序。 |