PMP考試每天一練--PMP考試試題-84
|
PMP考試試題一: Emphasizing which of the following activities has affected the most important to cost of quality? A. prevention B. Appraisal C. Measurement D. Rework 強調下列哪一項活動對質量成本會產生最重要的影響? A. 預防 B. 評估 C. 測量 D. 返工 PMP參考答案:A. 預防 PMP答案解析:質量管理引言 P228 PMP考試試題二: The project manager has completed the Plan Risk Responses process, and has identified risk response strategies with the team. The team’s manager has asked for the amount of risk reserves needed for the project. What is the FIRST thing the project manager should do? A. Create the risk reserves. B. Prioritize the list of risks. C. Create the overall risk rating for the project. D. Determine secondary risks. 項目經理已經完成了規劃風險應對過程,并與團隊一起識別了風險應對策略。團隊的經理想知道項目的風險儲備量是多少。項目經理首先應該做什么? A.制定風險儲備。 B.制定風險優先級清單。 C.制定項目整體風險等級。 D.確定次生風險。 審題:根據題干,已經進行了規劃風險應對,考慮接下來首先應該做什么以獲得項目的風險儲備量。 定位:規劃過程組·風險管理·11.5.2 規劃風險應對 解析:風險應對策略制定之后,另外一影響風險儲備的因素就是確定次生風險。制定風險儲備應在確定次生風險后,所以選項A錯誤。制定風險優先級及風險等級都在定性風險分析中已經確定,所以選項B、C錯誤。 PMP參考答案:D.確定次生風險。 |