PMP考試每天一練--PMP考試試題-84

轉載者:PMP團購網      發布時間:2017/4/21        點擊: 2821

PMP考試試題一:

Emphasizing which of the following activities has affected the most important to cost of quality?

A. prevention

B. Appraisal

C. Measurement

D. Rework

強調下列哪一項活動對質量成本會產生最重要的影響?

A. 預防

B. 評估

C. 測量

D. 返工

PMP參考答案:A. 預防

PMP答案解析:質量管理引言 P228

PMP考試試題二:

The project manager has completed the Plan Risk Responses process, and has identified risk response strategies with the team. The team’s manager has asked for the amount of risk reserves needed for the project. What is the FIRST thing the project manager should do?

A. Create the risk reserves.

B. Prioritize the list of risks.

C. Create the overall risk rating for the project.

D. Determine secondary risks.

項目經理已經完成了規劃風險應對過程,并與團隊一起識別了風險應對策略。團隊的經理想知道項目的風險儲備量是多少。項目經理首先應該做什么?

A.制定風險儲備。

B.制定風險優先級清單。

C.制定項目整體風險等級。

D.確定次生風險。

審題:根據題干,已經進行了規劃風險應對,考慮接下來首先應該做什么以獲得項目的風險儲備量。

定位:規劃過程組·風險管理·11.5.2 規劃風險應對

解析:風險應對策略制定之后,另外一影響風險儲備的因素就是確定次生風險。制定風險儲備應在確定次生風險后,所以選項A錯誤。制定風險優先級及風險等級都在定性風險分析中已經確定,所以選項B、C錯誤。

PMP參考答案:D.確定次生風險。

閱讀本文的人還閱讀了:
2017年PMP考試時間安排
2017年PMP考試相關注意事項
2017年PMP報考條件和報名流程
2017年PMP考試時間及全國考點
PMP考試內容和PMP考試題型
如何參加PMP考試?
PMP項目管理考試費用變更
PMP考試題庫

日韩精品一区二区三区三区免费_欧美理论片在线_久久精品人人做人人爽97 _欧美日韩亚洲视频

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 日本精品一区二区三区在线| 国产区欧美区日韩区| 国产精品国语对白| 国产精品入口尤物| 午夜精品一区二区三区在线观看 | 国产欧美日韩综合精品| 午夜精品在线视频| 国产99在线播放| 国产精品午夜国产小视频| 日本国产中文字幕| 婷婷五月综合缴情在线视频| 国产精品视频在线播放| 欧美久久在线观看| 亚洲精品国产精品久久| 国产精品美女免费视频| 久久久久久久久久久国产| 日韩免费黄色av| 午夜精品一区二区三区在线观看| 国产精品99一区| 国产精品一区二区在线观看| 久久久国产一区二区三区| 欧美亚洲第一页| 色综合久久久久久中文网| 中文字幕精品一区日韩| 国产精品美女久久久久av超清| 精品国产aⅴ麻豆| 久久久亚洲影院| 久久躁狠狠躁夜夜爽| 欧美大香线蕉线伊人久久国产精品| 天天爽天天狠久久久| 一区二区不卡视频| 91久久精品美女| 国产日韩av高清| 国产欧美日本在线| 国产精品视频免费观看| 国产日韩一区二区在线观看| 九色91视频| 国产欧美亚洲精品| 国产精品视频白浆免费视频| 国产欧美日韩在线播放| 国产精品毛片一区视频|