PMP考試試題一: All of the following are the responsibility of a project manager EXCEPT? A. Maintain the confidentiality of customer confidential information. B. Determine the legality of company procedures. C. Ensure that a conflict of interest does not compromise the legitimate interest of the customer. D. Provide accurate and truthful representations in cost estimates. 下列哪項不是項目經理的責任? A. 為客戶的信息保密 B. 決定公司的程序是否合法 C. 確保利益沖突不會損害客戶的合法利益 D. 在估算成本中提供準確可信的說明 PMP參考答案:B. 決定公司的程序是否合法 PMP答案解析:項目經理的責任 PMP考試試題二: A project manager is working on a major new product development project when a risk occurs that does not have a risk response plan. What should the project manager do? A. Hold a risk reassessment and plan a workaround. B. Inform management and communicate the new risk to the team. C. Communicate the planned response to the stakeholder. D. Use some of the reserves to accommodate the risk. 項目經理負責的新產品開發項目發生了一項風險,這項風險之前沒有制定應對計劃。項目經理應該怎么做? A. 進行風險評估,并制定權變措施。 B. 將新風險通知給管理層。 C. 和干系人商談應對計劃。 D. 動用一些儲備。 審題: 本題的關鍵字是“發生了一項風險”和“沒有制定應對計劃”,顯然是與風險管理有關,考察的是當未識別出的風險發生之后,項目經理應該如何應對。 定位: 監控過程組·風險管理·11.6 控制風險 解析: 這里要借鑒控制風險中用到的輸入輸出和工具。在項目過程中監控到新的風險發生,應該先評估風險的影響(工具)。同時由于沒有應對計劃,應該及時指定權變措施(輸出)。 PMP參考答案:A. 進行風險評估,并制定權變措施。 |