PMP考試每天一練--PMP考試試題-21
|
PMP考試試題一: The project is close to completion. All project deliverable have been accepted by the stakeholders. The program manager has asked the project manager to take on another project. All external contracts have been met and all the contracts closed. What should the project manager do? A. Announce the project is closed and move to the new project. B. Ensure that all procedures to transfer the project’s products and service to production are in place. C. Conduct an external review of the project by a team of experts. D. Ensure the remaining project activities are transferred to the new project 項(xiàng)目已完成,所有項(xiàng)目可交付成果都已經(jīng)獲得項(xiàng)目干系人的驗(yàn)收。所有外部合同都已經(jīng)滿足,所有合同已經(jīng)結(jié)束。項(xiàng)目集經(jīng)理讓項(xiàng)目經(jīng)理處理另外一個(gè)項(xiàng)目,項(xiàng)目經(jīng)理應(yīng)該做什么? A. 宣布項(xiàng)目結(jié)束,并轉(zhuǎn)到管理新項(xiàng)目。 B. 確保將項(xiàng)目產(chǎn)品或服務(wù)轉(zhuǎn)到生產(chǎn)的所有程序均以就位 C. 由專家組對(duì)項(xiàng)目執(zhí)行外部審查。 D. 確保剩余的項(xiàng)目活動(dòng)轉(zhuǎn)到新項(xiàng)目中 PMP參考答案:C. 由專家組對(duì)項(xiàng)目執(zhí)行外部審查。 PMP答案解析:結(jié)束采購(gòu)-工具與技術(shù)-采購(gòu)審計(jì) (12.4.2.1)P388 PMP考試試題二: 下列各項(xiàng)除哪項(xiàng)外,是有關(guān)“基層估算”(grassrootsestimate)的正確陳述? a.其準(zhǔn)確率范圍為-5%到+10% b.也稱做工程估算 c.它主要用于工作分解結(jié)構(gòu)的第一級(jí) d.可能需花費(fèi)數(shù)月時(shí)間編制它 PMP正確答案:c.它主要用于工作分解結(jié)構(gòu)的第一級(jí) |