PMP考試練習(xí)--合同與采購(gòu)管理(21-25題)
|
合同與采購(gòu)管理-PMP考試章節(jié)練習(xí)(21-25題) 21. A contractor is hired on a CPFF basis. The estimated cost of the contract is $100,000; however, at completion the contract costs total $125,000. The agreed upon percentage profit paid to the contractor is 15%. How much will the contractor receive? 承包商在CPFF 的條件下受雇,合同估計(jì)的成本是$100,000,但是項(xiàng)目實(shí)際完成時(shí)花費(fèi)了$125,000 。已經(jīng)同意的支付給承包商的利潤(rùn)率是15%。承包商將得到多少? 22. A contractor is hired to construct a storage shed. The performance cost is $1,500, with $6,500 in materials, and a 50% incentive fee. The contractor completes the storage shed in 130 hours, with a materials cost of $6,200. The contractor is paid $7,850 at completion. What type of contract is being used for this project? 一個(gè)承包商受雇建造一個(gè)存貨倉(cāng)庫(kù)。執(zhí)行成本是$1,500,原料是$6,500,以及50%的激勵(lì)酬金。承包商完成工程用了130 個(gè)小時(shí),消耗了$6,200 的材料。在完工時(shí),承包商獲得$7,850 的報(bào)酬。這個(gè)項(xiàng)目中使用了哪種合同形式? 23. A company is going into the procurement on a project and must decide what type of contract to use. This decision is made in what phase of the Acquisition Process? 公司在項(xiàng)目中即將開(kāi)采采購(gòu)并且必須決定采用何種合同形式,這一決定是在采購(gòu)過(guò)程的那個(gè)階段作出? 24. When a project’s contract is not fully executed caused by a direct fault of the seller, the owner is entitled to seek damages. What condition best describes this occurrence? 當(dāng)項(xiàng)目合同由于賣(mài)方直接過(guò)錯(cuò)而未能完全履行時(shí),業(yè)主有權(quán)尋求賠償金。哪個(gè)條款最好地描述了此種情形? 25. Administrative closure should take place: 項(xiàng)目管理收尾應(yīng)該發(fā)生在: PMP考試練習(xí)答案(合同采購(gòu)):21-25 ADABE |