以下城市均已開通:
關(guān)閉
當(dāng)前位置:PMP團(tuán)購網(wǎng) > PMP考試資料 > 正文

PMP考試練習(xí)-項(xiàng)目時間管理21-25題

轉(zhuǎn)載者:PMP團(tuán)購網(wǎng)      發(fā)布時間:2014/8/14        點(diǎn)擊: 4057

PMP考試題庫之項(xiàng)目時間管理21-25題:

21. If task A has seven days of free float and 15 days of total float and the early start date is delayed 5 days, what does this do to the completion date of the project?
A. Delays the end date 10 days
B. Delays the early start date of the next dependent task five days
C. Allows the project to finish five days earlier
D. The finish date doesn’t change
如果任務(wù)A 有7 天的自由浮動時間和15 天總浮動時間,并且最早開始時間延誤了5 天,這對項(xiàng)目的完成日期有何影響?
A. 完成時間延遲10 天
B. 使下一個相關(guān)的活動的最早開始時間延誤5 天開始
C. 項(xiàng)目的完成時間提前5 天完成
D. 完成時間不變

22. If Task B has 15 days of free float and 25 days of total float, and the early start date of Task B is delayed 30 days, how is the project affected?
A. The next dependent task’s start date will be delayed 15 days
B. This task will be dropped off the critical path
C. The duration of the task will be shortened 15 days
D. The completion date of the project will be pushed out 5 days
E. A andD
如果任務(wù)B 有15 天的自由浮動時間和25 天浮動時間,任務(wù)B 的最早開始時間延誤了30天,那么項(xiàng)目受什么樣的影響?
A. 下一個相關(guān)任務(wù)的開始時間將延遲15 天
B. 這個任務(wù)將不會成為關(guān)鍵路徑
C. 任務(wù)的工期將縮短15 天
D. 項(xiàng)目的完成時間延長5 天
E. A 和D

23. If task C has 0 days of free float and 0 days of total float, what does this mean to the project?
A. The project does not have adequate lead and lag times built in
B. The task is on the critical path
C. The duration of the task should be compressed
D. The dates for the task are not accurate
如果任務(wù)C 有0 天自由浮動時間和總浮動時間,那么這對于項(xiàng)目意味什么?
A. 項(xiàng)目沒有提前和滯后的時間
B. 這個任務(wù)是在關(guān)鍵路徑上
C. 這個任務(wù)的工期應(yīng)該壓縮
D. 任務(wù)的日期不準(zhǔn)確

24. A master schedule is developed for an executive presentation. What information must the PM gather to complete this schedule?
A. Dates of major activities
B. Summary level task budgets
C. Key milestones
D. Summary level task descriptions
E. A.C,D
控制性進(jìn)度是用于主管進(jìn)行演示的。為了完成這一計劃,項(xiàng)目經(jīng)理必須要得到什么樣的信息?
A. 主要活動的日期
B. 概要任務(wù)的預(yù)算
C. 關(guān)鍵里程碑
D. 概要任務(wù)的描述
E. A,C,D

25. What is one of the key problems with using crashing rather than fast tracking to compress project duration?
A. Personnel overlap
B. Budget constraints
C. Sub-dividing critical path tasks to work in parallel
D. Finish to start relationships are modified
E. Negotiating reduction of task durations
用趕工而不是快速跟進(jìn)來壓縮項(xiàng)目工期的一個主要應(yīng)該關(guān)注的問題是什么?
A. 人員重疊
B. 預(yù)算限制
C. 子關(guān)鍵路徑任務(wù)的并行工作
D. 完成一開始關(guān)系的變動
E. 協(xié)商縮短任務(wù)歷時

PMP認(rèn)證考試題參考答案:21-25  DEBEB

閱讀本文的人還閱讀了:
1、PMP考試難嗎? 
2、PMP考試時間是什么?
3、PMP考試題型及PMP考試難度  

網(wǎng)站sitemap

日韩精品一区二区三区三区免费_欧美理论片在线_久久精品人人做人人爽97 _欧美日韩亚洲视频

PMP團(tuán)購導(dǎo)航
遠(yuǎn)程PMP團(tuán)購
北京PMP團(tuán)購
上海PMP團(tuán)購
廣州PMP團(tuán)購
深圳PMP團(tuán)購
江浙PMP團(tuán)購
西部PMP團(tuán)購
其他城市團(tuán)購



PMP題庫
主站蜘蛛池模板: 日韩视频在线一区| 伊人久久大香线蕉精品| 亚洲综合视频一区| 欧美不卡视频一区发布| 久久精品午夜一区二区福利| 国产精品午夜av在线| 日韩在线中文视频| 国产精品美女视频网站| 日韩在线中文视频| 久久国产乱子伦免费精品| 欧美精品久久久久久久自慰| 综合操久久久| 国产精品露脸av在线| 日韩精品资源| 国产精品情侣自拍| 黄色片视频在线播放| 国产欧美一区二区三区在线看| 国产一区二区视频在线免费观看| 91精品久久久久久久久久另类| 欧美国产日韩激情| 久久久精品电影| 中文视频一区视频二区视频三区| 久久久精品在线观看| 欧美日韩大片一区二区三区| 国产www精品| www亚洲精品| 亚洲最大福利网| 国产精品欧美久久久| 久久久亚洲天堂| 美日韩精品免费观看视频| 久久久91精品国产| 日韩高清国产一区在线观看| 欧美精品一本久久男人的天堂| 国产欧美日韩中文字幕| 国产精品第一视频| 亚洲专区中文字幕| 国产精品美女在线观看| 99在线免费观看视频| 日日骚久久av| 伊人婷婷久久| 久久久精品日本|