PMP考試練習-項目時間管理16-20

轉載者:PMP團購網      發布時間:2014/8/12        點擊: 3107

PMP考試題庫之項目時間管理16-20題:

16. Timely decisions directly affect the ability of the project team to meet commitments to cost and schedule constraints. Therefore:
A. the project team must be able to make decisions or obtain fast decisions from upper management
B. functional departments should make their decisions as quickly as possible
C. upper management should communicate decisions to the project team at least weekly
D. since consensus decision making is time consuming, provisions have been made for budget and schedule revisions
E. AandC
及時的決策直接反映了項目團隊完成成本和進度要求的能力。因此:
A. 項目團隊必須能夠做出決策或者從高層管理獲得快捷的決策
B. 職能部門應該盡快的做出決策
C. 高層管理應該至少每周與項目團隊進行溝通
D. 因為取得大家的一致同意是費時間的,只要按時在預算內提供就可以
E. A 和C

17. For a well planned project the project schedule is:
A. The agenda for carrying out the plan or a portion of it
B. Not important, as each team member acts according to plan
C. Used to generate a time table of major commitments for the project
D. B andC
對于一個計劃良好的項目,項目進度是
A. 實施計劃或者其中一部分的日程安排
B. 不重要,因為每個團隊成員按照計劃行動
C. 用于生成一個項目主要交付物的時間表
D. B 和C

18. The project plan is developed by:
A. The project manager
B. The manager of project managers
C. The project team
D. Top management
E. A andC
項目計劃是由______ 制定的:
A. 項目經理
B. 項目經理的上層經理
C. 項目團隊
D. 高層管理
E. A 和C

19. Planning and scheduling are:
A. Separate and distinct tasks and have little relationship to each other
B. The only means for assuring project resource
C. Distinct but inseparable aspects of the successful project
D. Tasks which take place in parallel in a project environment
計劃和進度安排是:
A. 是獨立的,有各自的任務,并且之間沒有什么關系
B. 是確保項目資源的唯一方法
C. 區別的,但是一個成功項目不可分割的方面
D. 在項目環境中并行發生的任務

20. The Time Management Function as it relates to personnel:
A. refers primarily to the manner in which the project manager and the various functional contributors to the project manage their time on a daily basis:
B. should not be over emphasized because it develops a “clock-watching” mentality in the project team.
C. Consists of four overlapping processes: planning, estimating, scheduling, and controlling
D. Consists of two overlapping processes: planning and controlling
與人有關的時間管理功能:
A. 首先指項目經理和其他各職能人員在項目中管理他們日常時間的方式
B. 不要過分強調,因為會在團隊中養成“等著下班時間到來”的一種習慣
C. 包括了四個重疊的過程:計劃、估算、進度安排和控制
D. 包括了兩個重疊的過程:計劃和控制

PMP認證考試題參考答案:16-20 ACECC

閱讀本文的人還閱讀了:
1、PMP考試難嗎?
2、PMP考試題型及PMP考試難度
3、PMP考試時間是什么?

日韩精品一区二区三区三区免费_欧美理论片在线_久久精品人人做人人爽97 _欧美日韩亚洲视频

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 国产传媒久久久| 欧美日韩一区二区在线免费观看| 国产精品香蕉国产| 久久久久久国产精品久久| 国产va免费精品高清在线 | 亚洲最新免费视频| 欧美亚洲黄色片| 国产极品在线视频| 欧美极品第一页| 久久精品久久精品国产大片| 欧美日韩国产高清视频| 色婷婷成人综合| 色综合天天综合网国产成人网| 国产精品亚洲精品| av久久久久久| 中文字幕免费在线不卡| 久久久久久91香蕉国产| 国产日韩欧美日韩| 视频一区不卡| 视频一区二区三区在线观看| 久久久久亚洲精品国产| 国产精品黄视频| 九九精品在线播放| 国产在线观看福利| 色妞在线综合亚洲欧美| 国产日韩中文字幕在线| 日本婷婷久久久久久久久一区二区 | 日韩av一区二区三区在线| 国产欧美欧洲| 欧美久久在线观看| 久久久人人爽| 亚洲图片在线观看| 久久中文精品视频| 亚洲综合中文字幕在线| 国产精品91久久久| 在线精品亚洲一区二区| 国产成人av在线播放| 精品欧美日韩在线| 国产欧美欧洲在线观看| 色综合色综合网色综合| 五月天色婷婷综合|